Portfolio

UTILITIES ENGINEERING SAMPLE PROJECTS

2023 | HEB Austin 33 WWTP & Irrigation Field Design

Parra & Co was engaged by HEB to perform the Engineering Design of their Wastewater Treatment Plant (WWTP) and Irrigation field for their new Austin 33 store. 

For Phase I of this project, the Parra & Co team researched the site with the intent of providing a conceptual sizing of the drip field for a 14,000 gpd on site WWTP that will serve the new HEB store and produce our Preliminary Engineering Report (PER). This PER included a comparison between a conventional activated sludge system and a sequence match reactor that complies with the existing Texas Land Application Permit. (TLAP)

During phase II, Parra & Co provided the performance specifications and Construction Documents for the WWTP system and Irrigation Field. Our team also provided assistance with permitting, construction inspection, startup, and post-construction/warranty. Parra & Co received approval of the system from TCEQ in October 2021. This endeavor concluded successfully with the plant opening on June 20, 2023 and the new HEB Austin 33 store opening to the public the following month on July 6.

2019 | City of Mercedes W/WW Facilities Conditions Assessment

Parra & Co performed a Water / Wastewater Facilities Conditions Assessment to support the City of Mercedes’ evaluation of transitioning utility operations from a third-party operator to a City-run Utilities Department. The study was intended to identify current conditions, operational gaps, and the level of effort required for the City to assume responsibility for its water and wastewater systems.

Our team conducted multi-day site visits to develop an inventory-based assessment of utility assets, facilities, equipment, records, operational costs, maintenance agreements, and staffing structure. Based on those findings, we provided recommendations related to staffing needs, organizational structure, minimum qualifications for future personnel, a conceptual chart of accounts, implementation timeline, budget considerations, levels of operation, quality control, and assumed risk. Parra & Co also supported a workshop to review the findings and help guide next-step decision-making.

2021 | Zacate Creek WWTP TPDES Permit Renewal

Parra & Co was engaged by the City of Laredo to provide professional engineering services for the Texas Pollutant Discharge Elimination Systems (TPDES) permit renewal for the Zacate Creek Wastewater Treatment Plant (ZCWWTP).

Our team completed the appropriate application forms and prepared the required application attachments to renew the TPDES permit. While the application was being processed, our team assisted with responses to the Texas Commission on Environmental Quality (TCEQ) questions during the reviews. 

Parra & Co also provided Legal Permit Assistance regarding the renewal application and any possible issues raised by the existing compliance issues at the Zacate Creek Wastewater Treatment Facility (ZCWWTF), as well as any necessary legal analysis and evaluation during the preparation of the renewal application. Under the permit legal assistance, our team performed quality assurance and regulatory review of the draft permit renewal application, including identification of any suggested revisions, prior to its submission to TCEQ. 

2020 | Preliminary Engineering Report for 60,000 GPD WWTP

Parra & Co was engaged by a private client to prepare the Preliminary Engineering Report, system engineering design, and permitting support for a wastewater treatment plant serving a planned 30-acre development in Corpus Christi, Texas. During the preliminary review, our team identified site discharge and drainage conditions requiring additional evaluation and incorporated those considerations into the project approach.

We developed the Preliminary Engineering Report to establish a conceptual understanding of the system and provide an order-of-magnitude construction cost. From there, Parra & Co supported permitting efforts, including TPDES-related coordination, and provided performance specifications for pre-selection of the conventional system along with construction documents for the wastewater treatment plant. Our scope also included technical recommendations, construction-phase support, startup assistance, and post-construction warranty coordination, helping move the project from early planning through implementation readiness.

2022 | South Laredo WWTP Operation & Maintenance Manuals and Training

Parra & Co, in collaboration with the City of Laredo and the South Laredo Wastewater Treatment Plant staff, developed an Operations & Maintenance Manual that fulfilled the requirements listed on the Texas Administrative Code Title 30, Part 1 Chapter 217, Sub-chapter A, Rule §217.16.

Based on the background information provided by the City of Laredo, (Preliminary Engineering Report, equipment manufacturer’s manuals, SCADA manual, Emergency Response Plan, Risk Management Plan, Hazardous Mitigation plans, as-built drawings, applicable change orders, applicable communication letters, and any other necessary information) Parra & Co segmented the process into logical sub-units. 

Examples of these sub-units being the normal start-up, routine, emergency, and shutdown procedures for the aeration basins (including the basins themselves); the diffusers, blowers, and power control systems, along with the hydraulic, air valves and piping associated with the basins. Similarly, the procedures for the clarifiers would include the RAS, WAS and scum pumps associated with the clarifiers along with any instruments, power, and controls.

These manuals were also delivered in a searchable pdf format for ease of use for the operators. Further, the Parra & Co team was composed of engineers and operators, creating a final product that was technically accurate and easy to use.

Scroll to Top